Owner/General Contractors Work Needed To Complete A Drop-Ship Home
While not including all on-site (field) items which must be
completed, the following is a comprehensive list of common
on-site functions to be completed by you the owner or your General Contractor
you Hire to complete your New Home: Your new home from the factory is about 85%
complete. This means you or your General Contractor will have to
finish the interior and exterior before you can occupy the home.
-
Land/Lot Development
-
Purchase
-
Clear Title (if
not already owned)
-
Accessible to
Modular Transporter (conduct site accessibility study)
-
Perk Test (or
public sewer if available)
-
Land Surveyed (if
not already owned)
-
Forms/Procedures/Permits
-
Select Modular
Model, Options
-
Develop and
Finalize Prints, Plans, Options, Finishes and Specs
-
Contracts Signed
-
Sign-Off on Plans
and Specs
-
Secure Financing
-
Set Target
Occupancy Date
-
Issue Deposit
-
Obtain and Post
Permits
§
Building
§
Electrical
§
Plumbing
§
Mechanical
§
Driveway
opening permit
§
Zoning
§
Other permits
required by local government
-
Application for Gas/Electrical Service
-
Site Survey (stake out)
-
Foundation and Site work
-
Order lolly Columns
-
Deliver Dumpster and Port-a-potty
-
Clear lot, Cut in Driveway to Foundation, install QP base.
-
Layout and Excavation
-
Form Footings
-
Footing Inspection
-
Pour Footings
-
Install Footing Drains and Basement Stone
-
Install Under-Slab Utilities
-
Block Delivery/Foundation Systems
-
Construct/Install Foundation Walls
-
Inspect Foundation Drains
-
Apply Foundation Damp-Proofing and Vapor Barrier
-
Install Anchor Clips/Bolts, Sill Plate and Sealer
-
Install Sump Pit
-
Install Basement Windows
-
Install Foundation Drain to Daylight
-
Backfill
-
Site Preparation
-
Foundations and Footings are Completed
-
Foundation is Square and Level
-
Foundation and Footings have passed Inspection
-
Obstacles for Crane and Transporters have been Removed
-
Access Route for Crane and Transporters is planned
-
Crane Pad is Ready and Firm
-
Set Crew and Crane Schedules are Confirmed
-
Bulldozer and Operator Scheduled and Confirmed
-
Utility Crews have been Scheduled for Turn-off / Turn-on (if applicable)
-
Weather Forecast for Set Day looks Adequate
-
Payment for Delivery Day Confirmed and Available by Bank or Owner.
-
Modular Home Set
-
Modules Delivered/Received
-
Unwrap Modules
-
Check Inventory of Ship-Loose Materials
-
Mark Mating Lines on the Foundation
-
Locate Pick-Points on the Modules, Prepare for Lifting
-
Module Set
-
Fasten and Check Module
-
Prepare Mating Surfaces
-
Prepare Wires, Pipes, Ducts and Stairs
-
Posts/Support Columns Set/Installed
-
Lift Jointed Roof Sections with Crane
-
Lift Dormers and Other Roof Elements
-
Make the Home Weather-Tight and Secure
-
Sign Set-Release
-
Pour Basement Floor
-
Stairs to Basement Set/Installed
-
Exterior Finishing
-
Siding Completed
-
Masonry Work Completed
-
Prime, Paint or Stain Exterior Surfaces
-
Install Shutters
-
Install Chimney Flues
-
Install Gutters and Downspouts
-
Optional Garages Completed
-
Optional Porches, Decks and Patios Completed
-
Interior Electrical
-
Install Circuit Breaker Box
-
Install Meter Box, Conduit Master, Service Entrance Cable & Basement Cable
-
Connect Wiring of Modular Units and Tie-In to Junction Box
-
Connect Service in Garage and Outbuildings if Applicable
-
Install Sump Pump (Optional)
-
Install 220v Service for Range/Dryer (Optional)
-
Electrical Inspection
-
Plumbing Connections
-
Drill/Install Well & Pump or Hook-Up to Public System
-
Install/Inspect Septic and Drainage Systems of Hook-Up to Public Systems
-
Install Shower Doors (if Shipped Loose)
-
Install Supply and Drain Lines/Connect to Stubbing (also Between Floors if
Required)
-
Connect Roof Vent Stubbing through Roof.
-
Install Gas Pipes to Range/Dryer/Water Heater/Furnace if Applicable
(Optional)
-
Install Exterior Gas Stub for Natural/Propane Gas (Optional)
-
Check and Tighten Shut-Off Valves
-
Plumbing Inspection
-
HVAC
-
Install/Connect AC System
-
Install Oil Tank and Line to Furnace (Optional)
-
Install Electric Water Heater and Connect to Breaker Box (Optional)
-
Connect Chimney Flue Into Furnace (Optional)
-
Vent Dryer
-
Mechanical Inspection
-
Interior Finishing
-
Finish/Patch Drywall
-
Paint Interior Walls
-
Finish Interior Trim and Doors/Adjust
-
Install or Seam Vinyl, Hardwood, Laminate or Carpeting at Mate Walls
-
Clean-Up
-
Exterior Final Finish
-
Complete Garage Floors, Steps, Service Walks, etc.
-
Install Exterior Lights and Bulbs
-
Finish Grading
-
Landscaping
-
Garage Doors
-
Exterior Clean-Up
-
Closing
-
Punch List
-
Final Clean-up - Remove Dumpsters & Port-a-potty
-
Walk Through
-
Final Building Inspection
-
Occupancy Permit
|